Request for Statement of Qualifications (SOQ) for
Town of Many, Louisiana
SOQ # 1
SOQ SUMMARY: The Town of Many, Louisiana is soliciting Statements of Qualifications (SOQs) from qualified firms to develop a Comprehensive Safety Action Plan (CSAP) in accordance with the U.S. Department of Transportation’s Safe Streets and Roads for All (SS4A) program. The CSAP will apply a Safe System Approach to identify and prioritize strategies, projects, and policies aimed at eliminating serious injuries and fatal crashes for all roadway users within the Town of Many. The CSAP will be data-driven, developed through stakeholder and community engagement, and position the Town of Many to pursue future funding and implementation opportunities that improve road safety outcomes.
SOQ ISSUE DATE November 17, 2026
SOQ DUE DATE December 18, 2026
PRE-SUBMITTAL CONFERENCE December 10, 2026, at 2 pm CST. It is highly recommended that all proposers attend the pre-submittal conference.
Location: Many Town Hall 965 San Antonio Ave, Many, LA 71449
DEADLINE FOR QUESTIONS The deadline for questions is December 9, 2026, at 4:00 p.m. CST. Questions and/or inquiries must be submitted in writing to Suzanne Williams, Grants Manager. Email questions to suzanne@manypolice.org. The Town will publicly post responses to questions on the Town’s website by December 14, 2026.
SOQ
SUBMISSION PROCESS SOQs may be submitted as a hard copy OR electronically. Any SOQ received after closing time will be returned unopened. The Town reserves the right to reject any and all SOQs. Documents, including the SOQ, Appendix, and crash data are posted to townofmany.org/rfps.
Hard-Copy Submissions: Sealed SOQs may be received at Town Hall, 965 San Antonio Ave., Many, LA 71449, until 3:00 p.m. on Friday, December 18, 2026, at which time they will be opened and publicly read aloud. SOQs should be on the firm’s letterhead and signed by the firm’s representative. SOQs received will remain sealed until opening. SOQs will not be received after the closing time and date. The sealed bid envelope should be plainly marked “SS4A SOQ” showing the firm’s name, opening date, and time.
Electronic Submissions: If submitted electronically, SOQs must be submitted at https://lamats.easibuy.com, until 3:00 p.m. on Friday, December 18, 2026, at which time they will be opened and read publicly aloud. Respondents must register at https://lamats.easibuy.com to access the SOQ and any related documents. There is no cost to register, to access documents, or to submit your response.
SOQ WEBSITES TownofMany.org/rfps or https://lamats.easibuy.com
CONTACT Suzanne Williams, Grants Manager, 318-715-4963
Summary
The Town of Many (the “Town) is soliciting Statements of Qualifications (SOQs) from qualified firms to develop a Comprehensive Safety Action Plan (CSAP) in accordance with the U.S. Department of Transportation’s Safe Streets and Roads for All (SS4A) program. The finalized CSAP will be a strategic, data-driven roadmap to eliminate traffic fatalities and serious injuries using USDOT’s Safe System Approach.
The CSAP will analyze crash data, roadway conditions, and systemic factors to identify high-priority opportunities to improve safety for all users in the jurisdiction, including pedestrians, bicyclists, and drivers. The CSAP will include a safety analysis, stakeholder engagement, focused attention to vulnerable road users (e.g., youth, older adults), clear and measurable goals, and a prioritized set of projects that position the Town of Many for future funding and implementation opportunities.
Background
The Town of Many, Louisiana was awarded a $304,000 SS4A planning grant by the USDOT in March 2026 to develop a Comprehensive Safety Action Plan (CSAP). The Town of Many provided a $76,000 local match, bringing the full project budget to $380,000. The finalized CSAP will provide a roadmap for the Town of Many to eliminate traffic fatalities and serious injuries within the jurisdiction. The Town of Many aims to have the final CSAP publicly available by December 1, 2027, and final SS4A report submitted to the federal government by January 1, 2028.
The Town of Many is the largest town within Sabine Parish, the Parish seat, and classified by the USDOT as both a Transportation Disadvantaged Community and an Economic Disadvantaged Community. Over the past five years, Sabine Parish has experienced 860 crashes and 23 traffic fatalities. Five intersections within the Town of Many have been identified as particularly dangerous, contributing to a high number of vehicle collisions and multiple motorist and pedestrian fatalities in recent years.
Intersection Crashes
U.S. Highway 171 & LA Highway 6 24
LA Highway 6 & LA Highway 1217 (Marthaville Rd.) 8
LA Highway 6 & Church Street 5
LA Highway 6 & Capitol Street 5
U.S. Highway 171 & Fisher Road 5
The Town’s roadways suffer from poor pavement quality, insufficient shoulder widths, and designs that are inconsistent with current traffic speeds, contributing to unsafe driving conditions. Key corridors connecting the local community lack sidewalks altogether or have narrow, deteriorated, and unsafe pedestrian pathways, limiting ADA accessibility and mobility for residents that use motorized wheelchairs. Persistent congestion affects several major corridors and increases safety risks. The Town of Many is seeking to develop a CSAP to determine strategies to reduce high crash rates and increase road safety for all residents.
Outcome Goals
The successful completion and implementation of the CSAP will play a key role in helping the Town of Many:
Achieve zero deaths recorded at five key intersections in the Town of Many.
Secure future funding to implement transportation safety projects.
Increase families and children walking and/or riding bikes to key destinations like school, work, downtown events, festivals and other gatherings.
Increase mobility and accessibility for residents, youth, seniors, and people with disabilities, allowing them to safely travel in town without concerns of being injured.
Increase community awareness of road safety challenges and opportunities to provide input on potential solutions.
Award Terms
The Town of Many intends to award one contract not to exceed $380,000. As stated in its USDOT SS4A grant agreement, the Period of Performance for this award is 24 months effective on September 28, 2026.
Scope of Services
The Town of Many’s grant application, titled “Develop a New Comprehensive Safety Action Plan,” is focused on creating a CSAP that establishes a cohesive vision for achieving a reduction in serious traffic injuries and fatalities. The purpose of this SOQ is to retain a consultant that will be responsible for conducting transportation safety analyses, developing associated data tools, and delivering a CSAP that identifies effective safety strategies for the Town of Many to implement as a part of future implementation projects.
The project requirements listed below will help ensure that the Town of Many completes all of the requirements listed by USDOT for developing a complete CSAP: https://www.transportation.gov/sites/dot.gov/files/2026-03/SS4A-FY26-Self-Certification-Eligibility-Worksheet.pdf
Project Requirements
To develop a comprehensive and meaningful CSAP, the selected consultant will be responsible for overseeing three core project tasks as part of the Scope of Services detailed in this section. These tasks include:
Overseeing project management & administration
Conducting existing conditions inventory and analysis
Drafting plan recommendations and final deliverables, including a final CSAP that will be released to the public and adopted by the Town Council.
Each major task is broken down into a series of sub-tasks as outlined below.
Task 1: Project Management & Administration
The selected consultant will be required to deliver the following project management deliverables to the Town of Many’s Grants Manager to ensure the Town of Many can track and report progress to internal and external stakeholders.
Task 1.1: Project Management
The selected consultant will provide proactive project management to ensure the CSAP is delivered on schedule, within budget, and in alignment with project goals. This includes setting up a project kick-off meeting with relevant stakeholders, maintaining a clear and up-to-date project schedule, tracking progress against key milestones, identifying and addressing risks or delays, and ensuring timely completion of action items.
The consultant will support effective coordination with the Town’s Grants Manager and other key stakeholders through regular communication and standing meetings, ensuring that project status, decisions, and next steps are clearly understood. The consultant will also prepare and equip the Grants Manager and other designated staff to deliver clear, accurate, and timely updates to leadership and governing bodies, as needed.
Throughout the project lifecycle, the consultant will facilitate productive meetings, provide strategic and administrative support for required engagements (e.g., Town Council or Task Force meetings), and ensure that all project management activities contribute to efficient decision-making and successful project delivery.
Task 1.2: Performance Monitoring, Reporting and Invoicing
The selected consultant will support ongoing performance monitoring and transparent quarterly reporting, with performance indicators developed collaboratively with the Grants Manager following contract award. The consultant will be accountable for clear communication, proactive risk identification and mitigation, and maintaining consistent visibility in project progress and outcomes.
To ensure that Town of Many and Federal Highway Administration (FHWA) expectations are clear and upheld throughout the study, the selected consultant is required to abide by and report on project performance measures set in the Town’s SS4A grant agreement.
The selected consultant is expected to help the Town’s Grants Manager prepare quarterly reports detailing project performance and provide information in a timely manner that allows adequate time to review materials prior to federal reporting deadlines. In addition, invoices must be submitted via email to the Grants Manager at Suzanne@manypolice.org and copied to tomclerk@cp-tel.net no later than the second week of the month following the month in which the services are provided.
Task 1.3: Town Leadership and Community Engagement
The selected consultant will support the Grants Manager in coordinating and engaging with Town leaders through the Town of Many’s SS4A Task Force. The SS4A Task Force is an advisory body comprised of the Town Leadership including the Mayor, Town Clerk, Grants Manager, Operations Manager, and representatives from the Police Department, Fire Department, EMS, School District, and Sabine Parish Chamber of Commerce.
The purpose of convening the Task Force is to ensure the CSAP is developed in alignment with Town priorities and to deliver a public commitment to an eventual goal of zero roadway fatalities and serious injuries. The public commitment should include either setting a target date to reach zero or achieve a reduction in roadway fatalities and serious injuries. The consultant is expected to engage with the Task Force at least once a month, and ensure members are equipped with clear, timely, and actionable information.
The selected consultant will also design and implement a community outreach strategy that builds broader public awareness, facilitates two-way engagement, and produces actionable insights to guide the CSAP’s development, project prioritization, and implementation. The goal of public education and outreach is to ensure that the CSAP is informed by meaningful, inclusive, and representative community input, particularly from populations disproportionately impacted by traffic safety risks.
Types of public education and outreach activities may include but are not limited to attending community events and festivals, and utilizing the Town website, social media, newspapers, and radio. The selected consultant will integrate feedback from both the SS4A Task Force and the community into project direction, key decisions, and final deliverables.
Task 2: Existing Conditions Inventory and Analysis
The selected consultant will analyze the built environment and policy context in Many, Louisiana, to pinpoint gaps hindering the Town from implementing a Safe System Approach. Findings will be compiled into tools and reports outlined in Task 3: Plan Recommendations and Final Deliverables.
Task 2.1: Data Identification and Preparation
The selected consultant is expected to develop a comprehensive baseline analysis by obtaining available crash data, disaggregated by mode, built environment, land use, and demographics. Data sources may include, but are not limited to: Roadway and other contextual data, existing local high-injury network datasets, Louisiana Department of Transportation (LaDOTD) crash data, land use shapefiles, hospitalization and transportation-related public health data, model inventory of roadway elements, U.S. Census Bureau or other relevant authoritative datasets, zoning maps, and other data sources as deemed appropriate by the selected consultant.
Task 2.2: High Injury Network Map
The selected consultant will use five years of the most recent crash data to produce an interactive High Injury Network (HIN) map to identify and prioritize high-crash corridors and intersections with a disproportionate concentration of fatal and serious injury crashes in Many. The HIN will be used to inform project prioritization and implementation strategies as part of the CSAP. The consultant will establish and document a clear, defensible methodology for developing the HIN, including data sources, analytical approach, and prioritization criteria.
The Town of Many expects that the HIN will incorporate data layers from Task 2.1: Data Identification and Preparation into the HIN data map to identify areas most affected by safety gaps. This might include school zones, senior and adult care facilities, and recreational spaces.
Minimum data points for the HIN should include:
Identification and prioritization of high-risk intersections and corridors based on fatal and serious injury crashes
Baseline spatial data depicting the location and frequency of fatal and serious injury crashes
Analysis of contributing factors (e.g., impairment, distraction, speeding, etc.)
Analysis of crash conditions (e.g., weather, time of day) and relevant historical trends
Mode-specific analysis (e.g., motorist, pedestrian, bicyclist, motorized wheelchairs)
Relevant roadway and infrastructure characteristics associated with crash locations (e.g., median, 4-way intersection)
Data for the HIN should be built into a user-friendly map, accompanied by underlying GIS data and documentation sufficient to support ongoing use, updates, and integration into Town systems.
Task 2.3: Systemic Safety Analysis
The selected consultant will conduct a Systemic Safety Analysis for the jurisdiction as defined by FHWA’s Quick Start Guide. The purpose of the Systemic Safety Analysis is to identify roadway characteristics and risk factors associated with crashes and prioritize safety improvements where severe crashes are most likely to occur.
The analysis conducted should cover the entire jurisdiction and should include, at minimum:
Five years of Town of Many crash data
Target crash type identification: the greatest number and type of severe crashes across transportation network, including datasets produced for the HIN
Focus facility type identification: disaggregation of target crash types by similar roadway characteristics, such as number of lanes or posted speed limits
Roadway factor evaluation: a summary of built environment characteristics present at locations experiencing higher than anticipated frequencies of crashes and injuries
The selected consultant is expected to scale the systemic safety analysis throughout the entire jurisdiction of Many. Data is expected to be retained and transferred to the Town of Many as described in Task 3.4: Final CSAP Development & File Transfer.
Task 2.4: Road Safety Audits
Utilizing findings from the HIN and Systemic Safety Analysis, the selected consultant is expected to conduct field assessments of priority corridors and intersections via a Road Safety Audit (RSA). The selected consultant is encouraged to use new and existing technology to support field data collection and analysis, including mobile applications, speed feedback signage, video analytics, or other intelligent transportation systems.
The selected consultant is expected to develop a field observation methodology that follows best practices, such as those identified within the FHWA’s Road Safety Audit Guidelines. The methodology needs to be clearly documented for later replication by the Town of Many.
Site observations should consider:
Roadway geometrics and conditions (e.g., clear zone hazards, curve radius, lane and shoulder widths, sight distance)
Intersection operations (e.g., congestion, posted speeds, signal timing, turning movements, yielding to pedestrians)
Driver behavior (e.g., speeding, aggressive passing, red-light violations)
User and mode type (e.g., pedestrians, cyclists, motorized wheelchairs, passenger vehicles, school buses, commercial trucks)
Field observations are to be summarized with memorandums, supporting imagery, and geolocated datasets and are to be retained and shared with the Town of Many as outlined in Task 3.4: Final CSAP Development & File Transfer. Findings should also be embedded within Tasks 3.1-3.4 to recommend relevant countermeasures and funding mechanisms for safety improvements.
Task 3: Plan Recommendations and Final Deliverables
The selected consultant is expected to consolidate all findings and recommendations into tools and reports outlined below, as well as an accessible, user-friendly, and illustrative CSAP. The CSAP must be made publicly available and published on a public website.
Task 3.1: Prioritized and Comprehensive Project List
The consultant will provide a clear, prioritized, and comprehensive project list for the Town of Many using a prioritization methodology, informed by the quantitative and qualitative data collected via Task 1 and Task 2. The selected consultant will share the prioritization method with the Grants Manager and SS4A Task Force for review before incorporating it into the CSAP.
This list should not only include the types of projects to be undertaken to improve safety, but also the exact project locations within Many. In each project location, the consultant should provide a priority score and a summary of data findings. The selected consultant should identify appropriate countermeasures with interim quick build solutions, as well as longer-term solutions that require significant capital funding. The selected consultant should also identify additional planning that may need to be completed and potential funding sources for each future project.
Task 3.2: Safety Performance Measures Methodology
The selected consultant will develop a methodology, data tool(s), and a performance measurement system to create jurisdiction-specific road safety targets for the Town of Many. This includes tracking the following performance measure(s) in an Excel spreadsheet: number of serious crashes, number of motorized user serious injuries or fatalities, number of non-motorized user serious injuries or fatalities, crash severity, and crash type. The selected consultant will share the performance measurement methodology with the Grants Manager and SS4A Task Force for review before incorporating into CSAP.
Task 3.3: Corridor Evaluation and Countermeasures Toolkit
The selected consultant is expected to develop a repeatable methodology for staff at Town of Many to use to evaluate safety within specific roadway corridors. Corridor evaluation will consider, at minimum, location identification, needs assessment, safety countermeasures, and future funding sources. The selected consultant is expected to review countermeasures adopted by other Louisiana SS4A Awardees and FHWA’s Proven Safety Countermeasures to inform its methodology. The selected consultant will share the corridor evaluation methodology with the Grants Manager and SS4A Task Force for review before incorporating it into the Action Plan.
Task 3.4: Final CSAP Development & File Transfer
The selected consultant will integrate all project goals, data inventory and analyses, public outreach efforts, policy and planning recommendations, project prioritization, and identified next steps for implementation funding into one CSAP. The CSAP will also include the performance measures that will guide the implementation of future projects, including a list of short-term and long-term actions for the Town to pursue to work towards the goal of eliminating deaths and serious injuries in Many.
The document is to be designed in collaboration with the Grants Manager to ensure consistent use of the Town of Many’s branding. The CSAP must be prepared as a public-facing and accessible document suitable for online posting and compliant with federal accessibility requirements. The CSAP should be designed to ensure that all the core elements of a plan are included as outlined in USDOT’s SS4A eligibility checklist. All tools and reports identified in Tasks 3.1-3.3 should be included as appendices to the CSAP.
The selected contractor will store all data collected and generated as part of this project in a secure file-storage system. Prior to project closeout, the selected contractor will upload and transfer all project files associated with the final CSAP to the Town’s file-storage system, organized in clearly labeled folders. The Town also requests copies of project files in hard copies and on a flash drive.
Submission Instructions
Hard-Copy Submission
Sealed Statements of Qualification will be received at Town Hall (965 San Antonio Ave., Many, La 71449) until 3:00 p.m. CST on Friday, December 18, 2026. Each SOQ will be opened and publicly read aloud.
SOQs should be on the firm’s letterhead and signed by the firm’s representative. The sealed bid envelope should be plainly marked “SS4A SOQ” including the firm’s name opening date, and time (Friday, December 4, 2026, at 3:00 p.m. CST). The town reserves the right to reject any and all SOQs. Any SOQ received after closing time will be returned unopened.
Electronic Submission
If submitted electronically, SOQs will only be received at https://lamats.easibuy.com, until 3:00 p.m. on Friday, December 18, 2026. Each SOQ will be opened and publicly read aloud.
Respondents must register at https://lamats.easibuy.com to access the SOQ and any related documents. There is no cost to register, to access documents, or to submit your response. Questions related to using the electronic platform may be directed to the LaMATS eAuction and Bid Services electronic administrator at paul@lamats.net.
All general questions and/or inquiries must be submitted in writing to the Town’s Grants Manager, Suzanne Williams at suzanne@manypolice.org by no later than December 9, 2026, at 4:00 p.m. CST. The Town will publicly post responses to questions on the Town’s website no later than December 14, 2026.
Statement of Qualifications (SOQ) Content
Each respondent must submit a Statement of Qualifications (SOQ) as per the guidance below that provides clear, concise information demonstrating the firm’s qualifications, relevant experience, key personnel, organizational capacity, and understanding of the project.
To support fair and efficient evaluation, the SOQ shall be organized in the order listed below. Respondents should provide only the information requested. The Town of Many encourages concise responses that are no longer than 12 pages (single spaced, no smaller than 12-pt. font) in length. There is no cover letter required for this SOQ.
SOQ CHECKLIST
Minimum Qualifications:
Compliance with federal transportation requirements and Louisiana Department of Transportation & Development (LADOTD) engineering standards. See Appendix for more details. ☐
Firm Profile, Experience, Qualifications and Capacity:
Provide an overview of the organization, including mission, focus areas, and service locations
Summarize the firm’s history, staff size, and office locations
Describe the firm’s relevant resources, capabilities, qualifications, and areas of expertise related to:
Transportation safety analysis
Planning and engineering
Community engagement
Highlight prior experience working with public sector clients and stakeholders on similar projects
Describe experience coordinating multidisciplinary teams or stakeholders
Provide examples of how community engagement informed project decisions or strategies
Highlight projects where the worked helped a public partner move from planning to implementation
Identify any proposed subconsultants (e.g., transportation safety, engineering, planning, or community engagement) and clearly define their roles on the project
Describe the firm’s current workload and overall capacity to successfully deliver the project
Explain how the firm will allocate sufficient personnel and resources to complete the project on time and within budget ☐
Project Team and Key Personnel:
Provide an organizational chart illustrating the proposed team structure and reporting relationships
Include resumes for key personnel assigned to the project
Describe each key team member’s role, responsibilities, level of authority, and availability for the duration of the project
Identify any key staff and personnel on sub-contractor teams ☐
Project Understanding and Approach:
Describe the firm’s understanding of the project, including key objectives, challenges, and opportunities.
Present a clear and concise approach to project management.
Describe the proposed methodology for stakeholder engagement and community involvement, including strategies to reach diverse and underserved populations. Describe how community input will be incorporated into final recommendations and deliverables. ☐
Proposed Performance and Contract Management Approaches:
Describe a proposed plan for performance and contract management, including any potential KPIs that could be tracked. Make sure these KPIs match the goals for this project outlined in Outcome Goals section of this SOQ. ☐
How We Choose
Minimum Qualifications
Registered to conduct business in the State of Louisiana
Not debarred or suspended by the federal government, State of Louisiana, or Town of Many to enter into a contract agreement
Demonstrated experience completing SS4A planning projects
Experience working with Louisiana Department of Transportation & Development
Has current liability and workers compensation insurance certificates of coverage
Mandatory experience (necessary minimum experience or references)
Ability to abide by the engineering standards for federally funded street planning projects in Louisiana (federal requirements & Louisiana State Engineering Standards)
Evaluation Criteria
EVALUATION CRITERIA ALLOCATION %
Firm Experience, Qualifications, and Capacity
Alignment of the organization’s mission, focus areas, and service locations with the Town of Many’s priorities and project locations.
Demonstrated success working with public sector clients, the Louisiana Department of Transportation and Development (LADOTD), and stakeholders on similar projects, resulting in strong collaboration, effective project delivery, and outcomes that met or exceeded client and community expectations.
Demonstrated success of sub-consultants in contributing to past projects, including the specific value they added to project outcomes through their expertise and collaboration.
Transportation Safety Analysis Experience and Qualifications
Proven ability to lead the development of Comprehensive Safety Action Plans, Vision Zero plans, or similar roadway safety plans—particularly those aligned with USDOT SS4A requirements—that were actionable, competitive for future implementation funding, and resulted in implementable strategies and measurable safety improvements.
Effective application of a Safe System Approach, including conducting systemic safety analyses and advancing evidence-based strategies that informed decision-making and contributed to measurable reductions in roadway fatalities and serious injuries.
Strong track record of conducting data-driven safety analyses—including crash data analysis, network screening, and identification of high-injury networks—and translating findings into clear, actionable insights that supported targeted investments and led to effective safety improvements.
Planning and Engineering Experience and Qualifications
Proven ability to work with local governments of similar size, context, and capacity, resulting in strong partnerships and successful project delivery.
Experience working with local governments of similar size, context, and capacity that led to effective collaboration, responsive project delivery, and outcomes aligned with community needs and priorities.
Demonstrated effectiveness in coordinating and leading multidisciplinary partners—including transportation agencies, law enforcement, and public health agencies—to foster collaboration, align strategies, and achieve integrated, impactful project outcomes.
Community Engagement Experience and Qualifications
Proven ability to design and implement fair and accessible community engagement processes that achieved broad, representative participation and meaningfully informed project outcomes.
Experience engaging historically underserved populations and those disproportionately impacted by traffic safety issues, resulting in input that was clearly connected to project goals, priorities, and deliverables.
Effective use of a range of engagement methods (e.g., in-person, virtual, pop-up, multilingual outreach) to reach diverse audiences and increase participation across community groups.
Demonstrated ability to translate community input into actionable safety strategies that reflected community priorities and contributed to effective, implementable solutions. 50%
Project Team and Key Personnel
The evaluation will consider the qualifications and relevant experience of the proposed project manager and key team members assigned to the project:
Relevant experience of the project manager and key staff in leading roadway safety planning efforts that resulted in actionable plans, successful implementation, and measurable safety improvements.
Demonstrated expertise in transportation safety analysis, planning, engineering, and community engagement as applied to past projects, resulting in well-informed strategies and effective, implementable outcomes.
Proven ability of the team to collaborate effectively with government staff and stakeholders, leading to strong partnerships, aligned decision-making, and successful project delivery. 25%
Project Understanding and Management Approach
The evaluation will consider the proposer’s understanding of the project goals and the clarity, feasibility, and effectiveness of the proposed approach to completing the work:
Demonstrated understanding of the purpose and required elements of an SS4A Comprehensive Safety Action Plan.
Clarity and quality of the proposed methodology for completing the scope of work, including data analysis, safety strategy development, and plan preparation.
A clear approach to community and stakeholder engagement, including meaningful outreach to residents, community organizations, and vulnerable road users is aligned with the context, needs, and goals of Town of Many.
Integration of community considerations, ensuring the plan reflects the needs of historically underserved communities and those most affected by traffic safety issues in the Town of Many.
A clear approach to developing prioritized safety improvements and implementation strategies, including near-term and long-term actions. 15%
Performance and Contract Management Approaches
A clear, measurable approach for performance and contract management, including any potential KPIs that could be tracked.
Demonstration of how the proposed performance and contract management approaches clearly connect with the Outcome Goals and Scope of Services stated in this SOQ. 10%
Selection Process, Award, and Protest Procedures
Selection Schedule
Schedule
Event Date(s)
SOQ issue date November 17, 2026
Deadline for questions December 9, 2026 at 4:00 p.m. CST
Pre-submittal conference December 10, 2026
Responses to questions posted December 14, 2026
SOQs due December 18, 2026 at 4:00p.m. CST
Anticipated contract award date January 19, 2027
Anticipated contract execution date No later than January 29, 2027
Selection and Award Process
The Town of Many has established a selection committee that will be responsible for evaluating SOQs against the evaluation criteria laid out in the Evaluation Criteria section of this SOQ. The selection committee will be responsible for ranking all firms objectively based on their scores. The highest-ranked firm will be invited to negotiate a final contract. If a fair and reasonable fee with the most qualified firm cannot be negotiated, then negotiations with that firm shall be terminated and initiated with the next best qualified firm.
Terms and Conditions
See the Grant Agreement in the Appendix for additional information on the terms and conditions that pertain to the USDOT award funding this project.
Appendix
Signed grant agreement with USDOT
Intersections maps
Existing crash data
Federal transportation requirements and Louisiana Department of Transportation & Development (LADOTD) engineering standards
407.26
11/25
Cost of Notice: 528